Process Step | Date Initiated | Date Completed | Comments |
Received | 9/19/2022 | 9/19/2022 |
|
Reimbursement Authority | 9/19/2022 | |
|
WMR Request | 9/23/2022 | 10/3/2022 |
|
Transfer Initial Comment Period | 9/27/2022 | 10/27/2022 |
|
RA Applicant Agreement | 10/25/2022 | 10/25/2022 |
|
Draft PD Issued | 10/23/2023 | 10/23/2023 |
|
PD Issued | 1/2/2024 | 1/2/2024 |
|
PD Weekly Public Notice | 1/9/2024 | 1/9/2024 |
|
Final Order Issued | 3/13/2024 | 3/13/2024 |
|
Permit Superseding Issued | 3/13/2024 | 3/13/2024 |
Permit G-18863 Issued Supersedes Permit G-18395
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|