Process Step | Date Initiated | Date Completed | Comments |
Received | 9/22/2022 | 9/22/2022 |
|
Transfer Initial Comment Period | 10/4/2022 | 11/3/2022 |
|
WMR Request | 10/4/2022 | 10/5/2022 |
|
Draft PD Issued | 9/12/2023 | 9/12/2023 |
|
PD Issued | 8/9/2024 | 8/9/2024 |
|
PD Weekly Public Notice | 8/13/2024 | 8/13/2024 |
|
Final Order Issued | 10/3/2024 | 10/3/2024 |
|
Certificate Remaining Issued | 10/3/2024 | 10/3/2024 |
RR 98008 Issued Supersedes CERT 92360
|
Certificate Remaining Issued | 10/3/2024 | 10/3/2024 |
RR 98009 Issued Supersedes CERT 60745
|
Certificate Remaining Issued | 10/3/2024 | 10/3/2024 |
RR 98010 Issued Supersedes CERT 56506
|
Certificate Remaining Issued | 10/3/2024 | 10/3/2024 |
RR 98011 Issued Supersedes CERT 52618
|
CBU Received | 12/2/2024 | 12/2/2024 |
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|