Process Step | Date Initiated | Date Completed | Comments |
Received | 12/29/2022 | 12/29/2022 |
|
Transfer Initial Comment Period | 1/10/2023 | 2/9/2023 |
|
WMR Request | 1/10/2023 | 1/17/2023 |
|
Certificate Remaining Issued | 2/16/2023 | 2/16/2023 |
RR Cert 96910 issued supersedes Cert 79719
|
Final Order Issued | 2/16/2023 | 2/16/2023 |
|
CBU Received | 9/11/2023 | 9/11/2023 |
|
Proof to the Satisfaction | 11/16/2023 | 11/16/2023 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|