| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/5/2023 | 1/5/2023 |
|
| Reimbursement Authority | 1/5/2023 | 8/21/2025 |
|
| WMR Request | 1/18/2023 | 12/8/2023 |
|
| Transfer Initial Comment Period | 1/24/2023 | 2/23/2023 |
|
| RA Applicant Agreement | 3/15/2023 | 3/15/2023 |
|
| Draft PD Issued | 12/19/2024 | 12/19/2024 |
|
| PD Issued | 7/7/2025 | 7/7/2025 |
|
| PD Weekly Public Notice | 7/8/2025 | 7/8/2025 |
|
| Certificate Remaining Issued | 8/21/2025 | 8/21/2025 |
RR Cert 98513 Issued Supersedes Cert 76713
|
| Final Order Issued | 8/21/2025 | 8/21/2025 |
|
| Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
| CBU Due | 10/1/2027 | 10/1/2027 |
|