| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/23/2023 | 1/23/2023 |
|
| WMR Request | 1/25/2023 | 4/11/2023 |
|
| Transfer Initial Comment Period | 1/31/2023 | 3/2/2023 |
|
| GW Review Request | 4/24/2023 | 4/24/2023 |
|
| IR Issued(still DPD Code) | 6/28/2023 | 6/28/2023 |
|
| PFO Issued(still PRD Code) | 9/27/2023 | 9/27/2023 |
|
| PD Weekly Public Notice | 10/3/2023 | 10/3/2023 |
|
| Final Order Issued | 11/20/2023 | 11/20/2023 |
|
| Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
| Extension Application Received | 12/4/2025 | 12/8/2025 |
|
| Extension FO Issued | 1/2/2026 | 1/2/2026 |
|
| CBU Due | 10/1/2026 | 10/1/2026 |
|
| Extended Completion Date [Extension C Date] | 10/1/2027 | 10/1/2027 |
|
| CBU Due | 10/1/2028 | 10/1/2028 |
|