Process Step | Date Initiated | Date Completed | Comments |
Received | 2/3/2023 | 2/3/2023 |
|
WMR Request | 2/8/2023 | 2/22/2023 |
|
Transfer Initial Comment Period | 2/14/2023 | 3/16/2023 |
|
Draft PD Issued | 3/8/2024 | |
|
PD Issued | 7/29/2024 | 7/29/2024 |
|
PD Weekly Public Notice | 7/30/2024 | 7/30/2024 |
|
Certificate Remaining Issued | 9/16/2024 | 9/16/2024 |
RR 97870 Issued Supersedes CERT 84246
|
Final Order Issued | 9/16/2024 | 9/16/2024 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|