Process Step | Date Initiated | Date Completed | Comments |
Received | 5/10/2023 | 5/10/2023 |
|
Application to Split a Permit | 5/15/2023 | 5/15/2023 |
|
Draft Proposed Final Order | 5/25/2023 | 8/22/2023 |
|
WMR Request | 5/25/2023 | 6/26/2023 |
|
Application to Split a Permit Comment Period | 8/22/2023 | 9/22/2023 |
|
Proposed Final Order | 9/22/2023 | 12/18/2023 |
|
PFO Protest Period | 12/19/2023 | 2/2/2024 |
|
Final Order Issued | 2/2/2024 | 3/4/2024 |
|
Permit Superseding Issued | 3/4/2024 | 3/4/2024 |
Permit G-18862 Issued Supersedes Permit G-16291
|
Permit Superseding Issued | 3/4/2024 | 3/4/2024 |
Permit G-18861 Issued Supersedes Permit G-16291
|