| Process Step | Date Initiated | Date Completed | Comments |
| GW Review Request | 5/24/2023 | 12/18/2023 |
|
| Received | 5/24/2023 | 5/24/2023 |
|
| WMR Request | 5/24/2023 | 5/31/2023 |
|
| Transfer Initial Comment Period | 5/30/2023 | 6/29/2023 |
|
| Draft PD Issued | 11/22/2024 | 11/22/2024 |
|
| PD Issued | 5/16/2025 | 5/16/2025 |
|
| PD Weekly Public Notice | 5/20/2025 | 5/20/2025 |
|
| Final Order Issued | 7/29/2025 | 7/29/2025 |
|
| Certificate Remaining Issued | 7/29/2025 | 7/29/2025 |
RR 98309 Issued Supersedes CERT 52879
|
| Certificate Remaining Issued | 7/29/2025 | 7/29/2025 |
RR 98310 Issued Supersedes CERT 96715
|
| Completion Due (C Date) | 10/1/2029 | 10/1/2029 |
|
| CBU Due | 10/1/2030 | 10/1/2030 |
|