| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/23/2023 | 6/23/2023 |
|
| WMR Request | 6/29/2023 | 7/28/2023 |
|
| GW Review Request | 6/29/2023 | 12/28/2023 |
|
| Transfer Initial Comment Period | 7/11/2023 | 8/10/2023 |
|
| RA Applicant Agreement | 9/25/2023 | 9/25/2023 |
|
| Reimbursement Authority | 9/25/2023 | 11/27/2024 |
|
| Draft PD Issued | 3/28/2024 | 3/28/2024 |
|
| PD Issued | 6/10/2024 | 6/10/2024 |
|
| PD Weekly Public Notice | 6/11/2024 | 6/11/2024 |
|
| Certificate Remaining Issued | 11/27/2024 | 11/27/2024 |
RR 97422 Issued Supersedes CERT 40919
|
| Final Order Issued | 11/27/2024 | 11/27/2024 |
|
| Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
| CBU Due | 10/1/2027 | 10/1/2027 |
|