Process Step | Date Initiated | Date Completed | Comments |
Received | 7/21/2023 | 7/21/2023 |
|
ODFW Review | 7/25/2023 | 8/15/2023 |
|
WMR Request | 7/25/2023 | 8/14/2023 |
|
Transfer Initial Comment Period | 8/1/2023 | 8/31/2023 |
|
Certificate Confirming Issued | 5/30/2024 | 5/30/2024 |
CF 97781 Issued Supersedes CERT 10238
|
Certificate Confirming Issued | 5/30/2024 | 5/30/2024 |
CF 97782 Issued Supersedes CERT 10266
|
Certificate Remaining Issued | 5/30/2024 | 5/30/2024 |
RR 97783 Issued Supersedes CERT 10238
|
Certificate Remaining Issued | 5/30/2024 | 5/30/2024 |
RR 97784 Issued Supersedes CERT 10266
|
Final Order Issued | 5/30/2024 | 5/30/2024 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|