| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/23/2023 | 10/23/2023 |
|
| Reimbursement Authority | 10/23/2023 | 7/3/2025 |
|
| WMR Request | 10/27/2023 | 12/5/2023 |
|
| Transfer Initial Comment Period | 10/31/2023 | 11/30/2023 |
|
| RA Applicant Agreement | 11/3/2023 | 11/3/2023 |
|
| Draft PD Issued | 3/28/2024 | 3/28/2024 |
|
| PD Weekly Public Notice | 5/7/2024 | 5/7/2024 |
|
| PD Issued | 5/8/2024 | 5/3/2024 |
|
| Final Order Issued | 7/3/2024 | 7/3/2024 |
|
| Certificate Remaining Issued | 7/3/2024 | 7/3/2024 |
RR 97586 Issued Supersedes CERT 89109
|
| Extension Application Received | 7/28/2025 | 7/28/2025 |
|
| Extension FO Issued | 9/26/2025 | 9/26/2025 |
|
| Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
| CBU Due | 10/1/2026 | 10/1/2026 |
|
| Extended Completion Date [Extension C Date] | 10/1/2027 | 10/1/2027 |
|
| CBU Due | 10/1/2028 | 10/1/2028 |
|