Process Step | Date Initiated | Date Completed | Comments |
Received | 11/27/2023 | 11/27/2023 |
|
WMR Request | 11/29/2023 | 11/30/2023 |
|
Transfer Initial Comment Period | 12/5/2023 | 1/4/2024 |
|
Draft PD Issued | 2/27/2025 | 2/27/2025 |
|
PD Weekly Public Notice | 5/6/2025 | 5/6/2025 |
|
PD Issued | 5/6/2025 | 5/6/2025 |
|
Final Order Issued | 6/24/2025 | 6/24/2025 |
|
Certificate Remaining Issued | 6/24/2025 | 6/24/2025 |
RR 98501 Issued Supersedes CERT 91670
|
Certificate Remaining Issued | 6/24/2025 | 6/24/2025 |
RR 98502 Issued Supersedes CERT 91669
|
Completion Due (C Date) | 10/1/2026 | 10/1/2026 |
|
CBU Due | 10/1/2027 | 10/1/2027 |
|