| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/15/2024 | 7/15/2024 |
|
| ODFW Review | 7/22/2024 | 8/1/2024 |
|
| WMR Request | 7/22/2024 | 10/30/2024 |
|
| Transfer Initial Comment Period | 7/23/2024 | 8/22/2024 |
|
| Certificate Confirming Issued | 11/10/2026 | 11/10/2026 |
CF 99619 Issued Supersedes Cert 45063
|
| Certificate Confirming Issued | 11/10/2026 | 11/10/2026 |
CF 99620 Issued Supersedes Cert 56499
|
| Certificate Confirming Issued | 11/10/2026 | 11/10/2026 |
CF 99621 Issued Supersedes Cert 56500
|
| Certificate Remaining Issued | 11/10/2026 | 11/10/2026 |
RR 99622 Issued Supersedes Cert 45063
|
| Certificate Remaining Issued | 11/10/2026 | 11/10/2026 |
RR 99623 Issued Supersedes Cert 56499
|
| Certificate Remaining Issued | 11/10/2026 | 11/10/2026 |
RR 99624 Issued Supersedes Cert 56500
|
| Final Order Issued | 11/10/2026 | 11/10/2026 |
|