| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/2/2024 | 12/2/2024 |
|
| WMR Request | 12/4/2024 | 12/31/2024 |
|
| Transfer Initial Comment Period | 12/10/2024 | 1/9/2025 |
|
| Initial Review | 5/13/2026 | 5/26/2026 |
|
| Proposed Final Order | 6/26/2026 | 6/26/2026 |
|
| PFO Weekly Public Notice | 6/30/2026 | 6/30/2026 |
|
| PFO Protest Period | 6/30/2026 | 7/30/2026 |
|
| Automatic Final Order | 9/1/2026 | 9/1/2026 |
|
| Certificate Remaining Issued | 9/8/2026 | 9/8/2026 |
RR 99176 Issued Supersedes Cert 63823
|
| Certificate Remaining Issued | 9/8/2026 | 9/8/2026 |
RR 99177 Issued Supersedes Cert 82384
|
| Completion Due (C Date) | 10/1/2027 | 10/1/2027 |
|
| CBU Due | 10/1/2028 | 10/1/2028 |
|