| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/10/2025 | 1/10/2025 |
|
| WMR Request | 1/17/2025 | 11/26/2025 |
|
| Transfer Initial Comment Period | 1/28/2025 | 2/27/2025 |
|
| Draft PD Issued | 12/29/2025 | 12/29/2025 |
|
| Proposed Final Order | 6/22/2026 | 6/22/2026 |
|
| PFO Weekly Public Notice | 6/23/2026 | 6/23/2026 |
|
| PFO Protest Period | 6/23/2026 | 7/23/2026 |
|
| Automatic Final Order | 8/25/2026 | 8/25/2026 |
|
| Certificate Remaining Issued | 9/2/2026 | 9/2/2026 |
RR 99391 Issued Supersedes Cert 80705
|
| Certificate Remaining Issued | 9/2/2026 | 9/2/2026 |
RR 99392 Issued Supersedes Cert 81408
|
| Completion Due (C Date) | 10/1/2027 | 10/1/2027 |
|
| CBU Due | 10/1/2028 | 10/1/2028 |
|