| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/3/2025 | 2/3/2025 |
|
| Application to Split a Permit | 3/3/2025 | 3/3/2025 |
|
| Draft PFO Issued (Obsolete) | 3/5/2025 | 8/18/2025 |
|
| WMR Request | 3/5/2025 | 3/20/2025 |
|
| Application to Split a Permit Comment Period | 8/19/2025 | 9/19/2025 |
|
| Proposed Final Order | 9/19/2025 | 10/14/2025 |
|
| PFO Protest Period | 10/21/2025 | 12/5/2025 |
|
| Final Order Issued | 3/5/2026 | 3/5/2026 |
|
| Permit Superseding Issued | 3/5/2026 | 3/5/2026 |
Permit G-18960 Issued Supersedes Permit G-18862
|
| Permit Superseding Issued | 3/5/2026 | 3/5/2026 |
Permit G-18961 Issued Supersedes Permit G-18862
|
| Permit Superseding Issued | 3/5/2026 | 3/5/2026 |
Permit G-18962 Issued Supersedes Permit G-18862
|