| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/19/1995 | 7/19/1995 |
|
| WMR Request | 11/13/1995 | 11/13/1995 |
|
| Deficiency Letter | 11/14/2007 | 3/24/2008 |
|
| ODFW Review | 3/17/2008 | 3/24/2008 |
|
| Draft PD Issued | 3/25/2008 | 3/25/2008 |
|
| PD Issued | 3/31/2008 | 3/31/2008 |
|
| PD Weekly Public Notice | 4/8/2008 | 4/8/2008 |
|
| Final Order Issued | 5/27/2008 | 5/27/2008 |
|
| Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
| CBU Due | 10/1/2010 | 10/1/2010 |
|
| Certificate Remaining Issued | 9/22/2021 | 9/22/2021 |
RR Cert 95781 Issued supersedes cert 83307
|
| Certificate Remaining Issued | 9/22/2021 | 9/22/2021 |
RR Cert 95780 Issued supersedes Cert 83308
|
| Final Order Issued | 9/22/2021 | 9/22/2021 |
|