Process Step | Date Initiated | Date Completed | Comments |
Received | 10/5/1995 | 10/5/1995 |
|
WMR Request | 3/28/1996 | 3/28/1996 |
|
PD Issued | 6/13/2005 | 6/13/2005 |
|
Final Order Issued | 4/13/2006 | 4/13/2006 |
|
Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
CBU Due | 10/1/2008 | 10/1/2008 |
|
CBU Received | 1/15/2010 | 1/15/2010 |
|
Proposed Certificate Mailing | 9/9/2016 | 9/9/2016 |
|
Certificate Confirming Issued | 3/3/2017 | 3/3/2017 |
|