| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/11/1997 | 12/11/1997 |
|
| Transfer Initial Comment Period | 12/16/1997 | 1/15/1998 |
|
| WMR Request | 1/5/1998 | 1/5/1998 |
|
| Draft PD Issued | 8/20/2008 | 8/20/2008 |
|
| PD Issued | 9/2/2008 | 9/2/2008 |
|
| PD Weekly Public Notice | 9/9/2008 | 9/9/2008 |
|
| Final Order Issued | 11/6/2008 | 11/6/2008 |
|
| Certificate Confirming Issued | 11/6/2008 | 11/6/2008 |
|
| Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
| CBU Due | 10/1/2011 | 10/1/2011 |
|
| Final Order Issued | 7/20/2021 | 7/20/2021 |
|
| Final Order Issued | 9/28/2021 | 9/28/2021 |
|
| CBU Completeness Review | 10/1/2021 | 10/15/2021 |
|
| CBU Received | 10/1/2021 | 10/1/2021 |
|