| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/8/1998 | 6/8/1998 |
|
| WMR Request | 6/30/1998 | 6/30/1998 |
|
| Final Order Issued | 7/24/2003 | 7/24/2003 |
|
| Completion Due (C Date) | 10/1/2004 | 10/1/2004 |
|
| CBU Due | 10/1/2005 | 10/1/2005 |
|
| Extension Application Received | 1/28/2019 | 1/28/2019 |
|
| Extension FO Issued | 1/31/2019 | 1/31/2019 |
|
| CBU Received | 10/7/2019 | 10/7/2019 |
|
| Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
| Certificate Confirming Issued | 9/10/2021 | 9/10/2021 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|