Process Step | Date Initiated | Date Completed | Comments |
Received | 8/21/1998 | 8/21/1998 |
|
WMR Request | 8/29/2000 | 8/29/2000 |
|
Final Order Issued | 9/8/2000 | 9/8/2000 |
|
Extension FO Issued | 9/16/2005 | 9/16/2005 |
|
Extension FO Issued | 9/21/2005 | 9/21/2005 |
|
Extension FO Issued | 10/28/2008 | 10/28/2008 |
|
Extension Application Received | 9/28/2012 | 9/28/2012 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|
Extension Application Received | 9/21/2017 | 9/21/2017 |
|
Extension FO Issued | 10/13/2017 | 10/13/2017 |
|
Extension Application Received | 9/30/2022 | 9/30/2022 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
Extension FO Issued | 11/9/2022 | 11/9/2022 |
|
Extended Completion Date [Extension C Date] | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|