Process Step | Date Initiated | Date Completed | Comments |
Received | 9/8/1998 | 9/8/1998 |
|
WMR Request | 9/14/1998 | 9/21/1998 |
|
Transfer Initial Comment Period | 9/15/1998 | 10/15/1998 |
|
Deficiency Letter | 9/26/2006 | |
|
Draft PD Issued | 11/6/2006 | 11/6/2006 |
|
Deficiency Letter | 12/1/2006 | 12/12/2006 |
|
GW Review Request | 3/21/2007 | 3/21/2007 |
|
Draft PD Issued | 10/15/2008 | 10/15/2008 |
|
PD Issued | 7/7/2011 | 7/7/2011 |
|
PD Weekly Public Notice | 7/12/2011 | 7/12/2011 |
|
Final Order Issued | 8/30/2011 | 8/30/2011 |
|
Certificate Remaining Issued | 8/30/2011 | |
RR 83677 issued supersedes Cert 80759
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|