| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/13/1998 | 11/13/1998 |
|
| WMR Request | 11/23/1998 | 11/23/1998 |
|
| Transfer Initial Comment Period | 11/24/1998 | 12/24/1998 |
|
| Administrative Hold | 1/29/2007 | 6/16/2007 |
|
| Administrative Hold | 6/16/2007 | 9/10/2007 |
|
| Deficiency Letter | 9/10/2007 | 10/1/2009 |
|
| Draft PD Issued | 3/31/2010 | |
|
| PD Issued | 5/21/2010 | 5/21/2010 |
|
| PD Weekly Public Notice | 5/25/2010 | 5/25/2010 |
|
| Final Order Issued | 9/20/2010 | 9/20/2010 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| CBU Completeness Review | 6/30/2021 | 7/13/2021 |
|
| CBU Received | 6/30/2021 | 6/30/2021 |
|
| Certificate Confirming Issued | 3/10/2023 | 3/10/2023 |
|