Process Step | Date Initiated | Date Completed | Comments |
Received | 7/28/1999 | 7/28/1999 |
|
Transfer Initial Comment Period | 8/3/1999 | 9/2/1999 |
|
WMR Request | 9/20/1999 | 9/20/1999 |
|
Protested | 9/24/1999 | 9/24/1999 |
|
Protest Filed | 9/24/1999 | 10/24/1999 |
|
Protest Filed | 1/21/2000 | 2/20/2000 |
|
Protested | 1/21/2000 | 1/21/2000 |
|
Final Order Issued | 10/5/2018 | 10/5/2018 |
|
Final Order Issued | 1/23/2019 | 1/23/2019 |
|
Certificate Remaining Issued | 1/23/2019 | 1/23/2019 |
RR 93914 Issued Supersedes Cert 28524
|
Reconsideration Requested | 3/25/2019 | 3/25/2019 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|
Extension Application Received | 10/14/2024 | 10/14/2024 |
|