Process Step | Date Initiated | Date Completed | Comments |
Received | 3/23/2000 | 3/23/2000 |
|
Transfer Initial Comment Period | 3/28/2000 | 4/27/2000 |
|
WMR Request | 4/5/2000 | 4/5/2000 |
|
GW Review Request | 4/14/2000 | 4/14/2000 |
|
PD Issued | 11/1/2004 | 11/1/2004 |
|
Final Order Issued | 5/25/2006 | 5/25/2006 |
|
Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
CBU Due | 10/1/2008 | 10/1/2008 |
|
CBU Completeness Review | 4/11/2022 | 4/14/2022 |
|
CBU Received | 4/11/2022 | 4/11/2022 |
|
Proposed Certificate Mailing | 10/6/2023 | 10/6/2023 |
|
Certificate Confirming Issued | 12/29/2023 | 12/29/2023 |
|