Process Step | Date Initiated | Date Completed | Comments |
Received | 3/15/2001 | 3/15/2001 |
|
Transfer Initial Comment Period | 4/3/2001 | 5/3/2001 |
|
WMR Request | 4/3/2001 | 4/5/2001 |
|
PD Issued | 5/17/2006 | 5/17/2006 |
|
PD Weekly Public Notice | 5/23/2006 | 5/23/2006 |
|
Final Order Issued | 8/8/2006 | 8/8/2006 |
|
Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
CBU Received | 6/3/2009 | 6/3/2009 |
|
CBU Due | 10/1/2009 | 10/1/2009 |
|
Proposed Certificate Mailing | 12/6/2013 | 12/6/2013 |
|
Extension Application Received | 1/16/2014 | 1/16/2014 |
|
Extension FO Issued | 1/23/2014 | 1/23/2014 |
|
Completion Due (C Date) | 1/24/2014 | 10/1/2014 |
|
CBU Received | 10/31/2014 | 10/31/2014 |
|
Proposed Certificate Mailing | 5/12/2023 | 5/12/2023 |
|
Certificate Confirming Issued | 8/11/2023 | 8/11/2023 |
|