Process Step | Date Initiated | Date Completed | Comments |
Received | 3/29/2001 | 3/29/2001 |
|
Final Order Issued | 11/9/2001 | 11/9/2001 |
|
Completion Due (C Date) | 10/1/2003 | 10/1/2003 |
|
CBU Due | 10/1/2004 | 10/1/2004 |
|
Extension Application Received | 11/18/2014 | 11/18/2014 |
|
WMR Request | 12/11/2014 | 12/12/2014 |
|
Extension FO Issued | 2/13/2015 | 2/13/2015 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|
CBU Received | 11/9/2016 | 11/9/2016 |
|
CBU Due | 10/1/2017 | 10/1/2017 |
|
CBU Withdrawn | 1/7/2019 | 1/7/2019 |
|
Extension Application Received | 1/14/2019 | 1/14/2019 |
|
Extension FO Issued | 1/30/2019 | 1/30/2019 |
|
CBU Received | 5/31/2019 | 5/31/2019 |
|
Certificate Confirming Issued | 1/7/2020 | 1/7/2020 |
|
Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|