Process Step | Date Initiated | Date Completed | Comments |
Received | 1/16/2002 | 1/16/2002 |
|
WMR Request | 1/29/2002 | 3/3/2003 |
|
Transfer Initial Comment Period | 2/4/2002 | 2/4/2002 |
|
Draft PD Issued | 11/21/2008 | |
|
PD Issued | 12/30/2008 | 12/30/2008 |
|
PD Weekly Public Notice | 1/6/2009 | 1/6/2009 |
|
Certificate Remaining Issued | 4/24/2009 | |
|
Final Order Issued | 4/24/2009 | 4/24/2009 |
|
CBU Received | 10/27/2010 | 10/27/2010 |
|
Certificate Confirming Issued | 2/16/2016 | 2/16/2016 |
|