| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/30/2002 | 9/30/2002 |
|
| Transfer Initial Comment Period | 10/8/2002 | 11/7/2002 |
|
| WMR Request | 12/18/2002 | 12/18/2002 |
|
| ODFW Review | 2/8/2006 | 2/22/2006 |
|
| Draft PD Issued | 3/14/2006 | 3/14/2006 |
|
| Deficiency Letter | 4/1/2006 | |
|
| Draft PD Issued | 7/11/2006 | 7/11/2006 |
|
| Draft PD Issued | 7/17/2006 | 7/17/2006 |
|
| PD Newspaper Notice | 9/7/2006 | 9/7/2006 |
|
| PD Issued | 9/7/2006 | 9/7/2006 |
|
| PD Weekly Public Notice | 9/12/2006 | 9/12/2006 |
|
| Final Order Issued | 11/9/2006 | 11/9/2006 |
|
| CBU Received | 7/14/2011 | 7/14/2011 |
|
| Certificate Confirming Issued | 11/16/2011 | 11/16/2011 |
|
| Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
| CBU Due | 10/1/2014 | 10/1/2014 |
|