| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/10/2003 | 2/10/2003 |
|
| Transfer Initial Comment Period | 2/25/2003 | 3/27/2003 |
|
| WMR Request | 4/4/2003 | 4/4/2003 |
|
| GW Review Request | 5/12/2003 | 5/12/2003 |
|
| Final Order Issued | 7/26/2004 | 7/26/2004 |
|
| Final Order Issued | 8/17/2006 | 8/17/2006 |
|
| Completion Due (C Date) | 10/1/2006 | 10/1/2006 |
|
| CBU Received | 10/24/2006 | 10/24/2006 |
|
| CBU Due | 10/1/2007 | 10/1/2007 |
|
| Proposed Certificate Mailing | 5/2/2014 | 5/2/2014 |
|
| Certificate Confirming Issued | 8/1/2014 | 8/1/2014 |
|