Process Step | Date Initiated | Date Completed | Comments |
Received | 6/30/2003 | 6/30/2003 |
|
Transfer Initial Comment Period | 7/8/2003 | 8/7/2003 |
|
ODFW Review | 7/24/2003 | 7/24/2003 |
|
Reimbursement Authority | 12/8/2004 | 12/8/2004 |
|
WMR Request | 12/14/2004 | 12/14/2004 |
|
ODFW Review | 11/20/2006 | 12/5/2006 |
|
Draft PD Issued | 3/27/2007 | 3/27/2007 |
|
PD Issued | 10/17/2007 | 10/17/2007 |
|
PD Weekly Public Notice | 10/23/2007 | 10/23/2007 |
|
Final Order Issued | 1/3/2008 | 1/3/2008 |
|
Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
CBU Due | 10/1/2010 | 10/1/2010 |
|
CBU Received | 5/11/2015 | 5/11/2015 |
|
Certificate Confirming Issued | 5/18/2017 | 5/18/2017 |
|