| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/8/2004 | 1/8/2004 |
|
| Transfer Initial Comment Period | 2/10/2004 | 3/11/2004 |
|
| WMR Request | 2/17/2004 | 2/17/2004 |
|
| GW Review Request | 2/19/2004 | 2/19/2004 |
|
| Draft PD Issued | 8/28/2007 | 8/28/2007 |
|
| PD Issued | 5/27/2008 | 5/27/2008 |
|
| PD Weekly Public Notice | 6/3/2008 | 6/3/2008 |
|
| Final Order Issued | 9/12/2008 | 9/12/2008 |
|
| Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
| CBU Due | 10/1/2010 | 10/1/2010 |
|
| CBU Received | 12/5/2012 | 12/5/2012 |
|
| Proposed Certificate Mailing | 5/2/2014 | 5/2/2014 |
|
| Certificate Confirming Issued | 8/1/2014 | 8/1/2014 |
|