Process Step | Date Initiated | Date Completed | Comments |
Final Order Issued | 5/13/2004 | 12/18/2006 |
|
Received | 5/13/2004 | 5/13/2004 |
|
WMR Request | 5/20/2004 | 6/1/2006 |
|
GW Review Request | 5/20/2004 | 7/7/2004 |
|
ODFW Review | 5/20/2004 | 6/10/2004 |
|
Transfer Initial Comment Period | 5/24/2004 | 6/23/2004 |
|
WMR Request | 6/1/2006 | 6/1/2006 |
|
Draft PD Issued | 10/5/2006 | 10/5/2006 |
|
PD Newspaper Notice | 10/17/2006 | 10/17/2006 |
|
PD Issued | 10/17/2006 | 10/17/2006 |
|
Transfer Initial Comment Period | 10/24/2006 | 10/24/2006 |
|
PD Weekly Public Notice | 10/24/2006 | 10/24/2006 |
|
Final Order Issued | 12/18/2006 | 12/18/2006 |
|
CBU Received | 10/11/2007 | 10/11/2007 |
|
Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
CBU Due | 10/1/2009 | 10/1/2009 |
|
Certificate Confirming Issued | 6/28/2019 | 6/28/2019 |
|