| Process Step | Date Initiated | Date Completed | Comments |
| Final Order Issued | 5/13/2004 | 12/18/2006 |
|
| Received | 5/13/2004 | 5/13/2004 |
|
| WMR Request | 5/20/2004 | 6/1/2006 |
|
| GW Review Request | 5/20/2004 | 7/7/2004 |
|
| ODFW Review | 5/20/2004 | 6/10/2004 |
|
| Transfer Initial Comment Period | 5/24/2004 | 6/23/2004 |
|
| WMR Request | 6/1/2006 | 6/1/2006 |
|
| Draft PD Issued | 10/5/2006 | 10/5/2006 |
|
| PD Newspaper Notice | 10/17/2006 | 10/17/2006 |
|
| PD Issued | 10/17/2006 | 10/17/2006 |
|
| Transfer Initial Comment Period | 10/24/2006 | 10/24/2006 |
|
| PD Weekly Public Notice | 10/24/2006 | 10/24/2006 |
|
| Final Order Issued | 12/18/2006 | 12/18/2006 |
|
| CBU Received | 10/11/2007 | 10/11/2007 |
|
| Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
| CBU Due | 10/1/2009 | 10/1/2009 |
|
| Certificate Confirming Issued | 6/28/2019 | 6/28/2019 |
|