Process Step | Date Initiated | Date Completed | Comments |
Received | 5/19/2004 | 5/19/2004 |
|
WMR Request | 6/15/2004 | 6/17/2004 |
|
GW Review Request | 6/15/2004 | 11/18/2004 |
|
Transfer Initial Comment Period | 6/22/2004 | 7/22/2004 |
|
Reimbursement Authority | 10/14/2004 | 10/14/2004 |
|
RA Applicant Agreement | 12/23/2004 | 12/23/2004 |
|
WMR Request | 8/5/2005 | 8/10/2005 |
|
PD Issued | 11/1/2005 | 11/1/2005 |
|
Final Order Issued | 12/27/2005 | 12/27/2005 |
|
Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
CBU Due | 10/1/2008 | 10/1/2008 |
|
Proposed Certificate Mailing | 2/6/2009 | |
|
Certificate Confirming Issued | 5/8/2009 | 5/8/2009 |
|