| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/1/2004 | 6/1/2004 |
|
| ODFW Review | 6/15/2004 | 7/9/2004 |
|
| WMR Request | 6/15/2004 | 9/7/2004 |
|
| Transfer Initial Comment Period | 6/22/2004 | 7/22/2004 |
|
| PD Issued | 10/13/2005 | 10/13/2005 |
|
| Certificate Remaining Issued | 1/25/2006 | 1/25/2006 |
cert 81647
|
| Final Order Issued | 1/25/2006 | 1/25/2006 |
|
| Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
| CBU Due | 10/1/2008 | 10/1/2008 |
|
| Draft PD Issued | 8/24/2012 | 8/24/2012 |
|
| Extension FO Issued | 9/7/2012 | 9/7/2012 |
|
| Completion Due (C Date) | 9/13/2012 | 10/1/2013 |
|
| CBU Due | 10/1/2014 | 10/1/2014 |
|
| CBU Received | 1/28/2015 | 1/28/2015 |
|
| Certificate Confirming Issued | 3/25/2022 | 3/25/2022 |
|