Process Step | Date Initiated | Date Completed | Comments |
Received | 6/18/2004 | 6/18/2004 |
|
WMR Request | 6/28/2004 | 7/23/2004 |
|
ODFW Review | 6/28/2004 | 6/28/2004 |
|
Transfer Initial Comment Period | 6/29/2004 | 6/28/2004 |
|
Draft PD Issued | 5/26/2009 | |
|
PD Issued | 10/12/2009 | 10/12/2009 |
|
PD Weekly Public Notice | 10/20/2009 | 10/20/2009 |
|
Final Order Issued | 12/7/2009 | 12/7/2009 |
|
CBU Received | 5/31/2012 | 5/31/2012 |
|
Certificate Confirming Issued | 12/3/2012 | 12/3/2012 |
|
Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
CBU Due | 10/1/2016 | 10/1/2016 |
|