Process Step | Date Initiated | Date Completed | Comments |
Received | 8/30/2004 | 8/30/2004 |
|
Reimbursement Authority | 9/2/2004 | 9/2/2004 |
|
WMR Request | 9/2/2004 | 10/8/2004 |
|
GW Review Request | 9/2/2004 | 9/8/2004 |
|
Transfer Initial Comment Period | 9/7/2004 | 9/7/2004 |
|
RA Applicant Agreement | 9/29/2004 | 9/29/2004 |
Work Order #: R05-022D
|
PD Issued | 12/1/2004 | 12/1/2004 |
|
Final Order Issued | 2/9/2005 | 2/9/2005 |
|
Completion Due (C Date) | 10/1/2006 | 10/1/2006 |
|
CBU Due | 10/1/2007 | 10/1/2007 |
|
CBU Received | 6/17/2009 | 6/18/2009 |
|
Proposed Certificate Mailing | 5/13/2016 | 5/13/2016 |
|
Certificate Confirming Issued | 9/23/2016 | 9/23/2016 |
|