| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/17/2004 | 9/17/2004 |
|
| ODFW Review | 10/8/2004 | 12/2/2004 |
|
| WMR Request | 10/8/2004 | 10/26/2004 |
|
| Transfer Initial Comment Period | 10/12/2004 | 10/12/2004 |
|
| RA Applicant Agreement | 6/7/2005 | 6/7/2005 |
Work Order #: R05-22L
|
| Final Order Issued | 9/13/2005 | 9/13/2005 |
|
| CBU Received | 7/7/2011 | 7/7/2011 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| Proposed Certificate Mailing | 8/30/2013 | 8/30/2013 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|
| Certificate Confirming Issued | 1/24/2014 | 1/24/2014 |
|