| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/17/2005 | 2/17/2005 |
|
| WMR Request | 3/11/2005 | 4/15/2005 |
|
| ODFW Review | 3/11/2005 | 4/7/2005 |
|
| Transfer Initial Comment Period | 3/15/2005 | 3/15/2005 |
|
| Draft FO Issued | 10/14/2009 | 11/9/2009 |
|
| PD Issued | 12/10/2009 | 12/10/2009 |
|
| PD Weekly Public Notice | 12/15/2009 | 12/15/2009 |
|
| Final Order Issued | 1/15/2010 | 1/15/2010 |
|
| Certificate Remaining Issued | 1/15/2010 | |
RR Cert 85960 issued supercedes Cert 16648
RR Cert 85961 issued supercedes Cert 64511
|
| Certificate Remaining Issued | 7/26/2011 | 7/26/2011 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|