Process Step | Date Initiated | Date Completed | Comments |
Received | 3/18/2005 | 3/18/2005 |
|
GW Review Request | 3/24/2005 | 4/1/2005 |
|
WMR Request | 3/24/2005 | 4/19/2005 |
|
Transfer Initial Comment Period | 3/29/2005 | 3/29/2005 |
|
Reimbursement Authority | 3/31/2005 | 3/31/2005 |
|
RA Applicant Agreement | 5/9/2005 | 5/9/2005 |
Work Order #: R05-021O
|
PD Issued | 6/20/2005 | 6/20/2005 |
|
Final Order Issued | 8/11/2005 | 8/11/2005 |
|
Completion Due (C Date) | 10/1/2006 | 10/1/2006 |
|
CBU Due | 10/1/2007 | 10/1/2007 |
|