| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/5/2005 | 4/5/2005 |
|
| Transfer Initial Comment Period | 4/12/2005 | 4/12/2005 |
|
| WMR Request | 4/12/2005 | 5/6/2005 |
|
| GW Review Request | 4/12/2005 | 9/19/2005 |
|
| ODFW Review | 4/12/2005 | 5/10/2005 |
|
| ODFW Review | 8/23/2006 | 9/29/2006 |
|
| GW Review Request | 8/23/2006 | 9/19/2005 |
|
| WMR Request | 8/23/2006 | 9/19/2006 |
|
| Draft PD Issued | 10/23/2006 | 10/23/2006 |
|
| PD Newspaper Notice | 12/22/2006 | 12/22/2006 |
|
| PD Issued | 12/22/2006 | 12/22/2006 |
|
| PD Weekly Public Notice | 1/2/2007 | 1/2/2007 |
|
| Final Order Issued | 3/15/2007 | 3/15/2007 |
|
| Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
| CBU Received | 10/1/2009 | 10/1/2009 |
|
| CBU Due | 10/1/2009 | 10/1/2009 |
|
| Proposed Certificate Mailing | 2/28/2014 | |
|
| Certificate Confirming Issued | 6/6/2014 | 6/6/2014 |
|