| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/25/2005 | 4/25/2005 |
|
| WMR Request | 5/11/2005 | 5/24/2005 |
|
| GW Review Request | 5/11/2005 | 7/26/2005 |
|
| Transfer Initial Comment Period | 5/17/2005 | 5/17/2005 |
|
| Reimbursement Authority | 6/6/2005 | 6/6/2005 |
|
| Deficiency Letter | 9/27/2006 | |
|
| Draft PD Issued | 10/31/2006 | 10/31/2006 |
|
| PD Issued | 12/22/2006 | 12/22/2006 |
|
| PD Weekly Public Notice | 12/26/2006 | 12/26/2006 |
|
| Final Order Issued | 2/28/2007 | 2/28/2007 |
|
| Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
| CBU Due | 10/1/2009 | 10/1/2009 |
|
| CBU Received | 3/7/2016 | 3/7/2016 |
|
| Proposed Certificate Mailing | 11/20/2020 | 11/20/2020 |
|
| Certificate Confirming Issued | 10/1/2021 | 10/1/2021 |
|