Process Step | Date Initiated | Date Completed | Comments |
Received | 4/26/2005 | 4/26/2005 |
|
WMR Request | 5/11/2005 | 5/24/2005 |
|
GW Review Request | 5/11/2005 | 11/4/2005 |
|
Transfer Initial Comment Period | 5/17/2005 | 5/17/2005 |
|
Draft PD Issued | 6/17/2009 | 6/17/2009 |
|
PD Issued | 8/27/2009 | 8/27/2009 |
|
PD Weekly Public Notice | 9/1/2009 | 9/1/2009 |
|
Final Order Issued | 10/2/2009 | 10/2/2009 |
|
CBU Received | 9/30/2011 | 9/30/2011 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Certificate Confirming Issued | 11/1/2013 | 11/1/2013 |
|