| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/24/2005 | 5/24/2005 |
|
| WMR Request | 6/22/2005 | 6/27/2005 |
|
| Transfer Initial Comment Period | 6/28/2005 | 6/28/2005 |
|
| Draft PD Issued | 4/28/2010 | 4/28/2010 |
|
| PD Issued | 6/10/2010 | 6/10/2010 |
|
| PD Weekly Public Notice | 6/15/2010 | 6/15/2010 |
|
| Certificate Remaining Issued | 7/15/2010 | |
RR Cert 86439 issued supersedes Cert 83664
|
| Final Order Issued | 7/15/2010 | 7/15/2010 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| CBU Received | 10/18/2012 | 10/18/2012 |
|
| Certificate Confirming Issued | 12/20/2013 | 12/20/2013 |
|