Process Step | Date Initiated | Date Completed | Comments |
Received | 6/16/2005 | 6/16/2005 |
|
WMR Request | 6/30/2005 | 7/11/2005 |
|
GW Review Request | 6/30/2005 | 7/12/2005 |
|
Transfer Initial Comment Period | 7/5/2005 | 7/5/2005 |
|
Draft PD Issued | 6/7/2006 | 6/7/2006 |
|
Draft PD Issued | 1/22/2007 | 1/22/2007 |
|
PD Issued | 2/27/2007 | 2/27/2007 |
|
Final Order Issued | 5/8/2007 | 5/8/2007 |
|
Extension FO Issued | 10/15/2008 | 10/15/2008 |
|
Final Order Issued | 1/22/2010 | 1/22/2010 |
|
Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
CBU Due | 10/1/2011 | 10/1/2011 |
|