Process Step | Date Initiated | Date Completed | Comments |
Received | 6/17/2005 | 6/17/2005 |
|
WMR Request | 6/30/2005 | 7/20/2005 |
|
Transfer Initial Comment Period | 7/5/2005 | 7/5/2005 |
|
Draft PD Issued | 9/22/2006 | 9/22/2006 |
|
Deficiency Letter | 10/8/2007 | 10/17/2007 |
|
PD Issued | 10/29/2007 | 10/29/2007 |
|
PD Weekly Public Notice | 11/6/2007 | 11/6/2007 |
|
Final Order Issued | 12/13/2007 | 12/13/2007 |
|
Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
CBU Due | 10/1/2010 | 10/1/2010 |
|
CBU Received | 12/2/2011 | 12/2/2011 |
|
Certificate Confirming Issued | 6/7/2013 | 6/7/2013 |
|