| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/12/2005 | 7/12/2005 |
|
| Transfer Initial Comment Period | 7/19/2005 | 7/19/2005 |
|
| WMR Request | 7/25/2005 | 8/3/2005 |
|
| ODFW Review | 7/25/2005 | 8/19/2005 |
|
| Reimbursement Authority | 8/29/2006 | 7/20/2007 |
|
| RA Applicant Agreement | 9/20/2006 | 9/20/2006 |
Work Order #: R07-069K
|
| Draft PD Issued | 4/24/2007 | 4/24/2007 |
|
| PD Issued | 7/27/2007 | 7/27/2007 |
|
| PD Weekly Public Notice | 7/31/2007 | 7/31/2007 |
|
| Final Order Issued | 9/27/2007 | 9/27/2007 |
|
| Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
| CBU Due | 10/1/2009 | 10/1/2009 |
|
| Certificate Confirming Issued | 7/20/2015 | 7/20/2015 |
|
| CBU Received | 7/20/2015 | 7/20/2015 |
|