Process Step | Date Initiated | Date Completed | Comments |
Received | 8/25/2005 | 8/25/2005 |
|
Reimbursement Authority | 8/25/2005 | 8/25/2005 |
|
GW Review Request | 8/29/2005 | 9/9/2005 |
|
WMR Request | 8/30/2005 | 9/13/2005 |
|
Transfer Initial Comment Period | 9/6/2005 | 9/6/2005 |
|
RA Applicant Agreement | 9/19/2005 | 9/19/2005 |
Work Order #: R05-025V
|
PD Issued | 12/2/2005 | 12/2/2005 |
|
Final Order Issued | 2/7/2006 | 2/7/2006 |
|
Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
CBU Due | 10/1/2008 | 10/1/2008 |
|
CBU Received | 2/19/2009 | 2/19/2009 |
|
Proposed Certificate Mailing | 9/15/2016 | |
|
Certificate Confirming Issued | 3/3/2017 | 3/3/2017 |
|