| Process Step | Date Initiated | Date Completed | Comments |
| ODFW Review | 5/23/2011 | 11/5/2011 |
|
| Received | 5/23/2011 | 5/23/2011 |
|
| Reimbursement Authority | 5/23/2011 | 3/29/2012 |
|
| WMR Request | 5/23/2011 | 11/5/2011 |
|
| Transfer Initial Comment Period | 5/31/2011 | 7/1/2011 |
|
| RA Applicant Agreement | 9/23/2011 | 9/23/2011 |
|
| Draft PD Issued | 11/17/2011 | 11/17/2011 |
|
| PD Issued | 2/27/2012 | 2/27/2012 |
|
| PD Weekly Public Notice | 2/28/2012 | 2/28/2012 |
|
| Protest Filed | 3/29/2012 | |
|
| Administrative Hold | 4/10/2015 | |
|
| Final Order Issued | 10/28/2016 | 10/28/2016 |
|
| CBU Received | 4/13/2017 | 4/13/2017 |
|
| Certificate Confirming Issued | 11/3/2017 | 11/3/2017 |
|
| Certificate Confirming Issued | 11/8/2017 | 11/8/2017 |
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|